Document navigation

Perform Cutover

Before you begin

  • The migration task is in Ready for Cutover status.
  • If the source VM's network configuration is cloned, power off the source VM before cutover or verify that automatic source VM shutdown is configured to avoid IP address conflicts.

Procedure

  1. In the navigation pane, select O&M Management > Migration Tasks > All Tasks.
  2. On the All Tasks page, select the target migration task, and then click Actions > Cutover.
    After cutover starts, VM workloads switch to the target platform. If Auto Shut Down Source VM is enabled for the migration task, the system shuts down the source VM by using the selected shutdown method.
  3. Read and confirm the risk information, enter cutover as prompted, and click Confirm to Cutover.

Results

After submitting the cutover request, monitor its progress and result in the task list.