Synchronize a Migration Task

Before you begin

Ensure that the migration task status is "Synchronization Stopped", "Synchronization Failed", or "Ready for Cutover". Otherwise, you cannot perform the synchronization operation.

Procedure

  1. In the navigation pane, select Operations Management > Migration Task > All Tasks.
  2. On the All Tasks page, select the migration task that you want to synchronize, and then click Actions > Synchronize.
  3. In the Synchronize Migration Task dialog, select the synchronization mode.
    The following two synchronization modes are supported:
    • Incremental Sync: Only synchronizes data that has changed since the last synchronization.
    • Full Sync: Synchronizes all data of the VM. For migration tasks that have completed initial synchronization, the system performs a comparison scan before executing a full sync. This process may take a significant amount of time.
  4. Click OK.