Applicable Scenario
- Product:
ZCF - Component:
ZStack Cloud - Versions:
5.3.xand5.5.x - Operating system/repository types:
h84r/ky10sp3 - Deployment: dual management nodes
- Trigger condition: upgrade the platform to
5.5.xfor supportedsriovfeatures and bringqemu/libvirtto the new LTS versions.
Symptoms
- The current platform version is
5.3.x. - The target version is
5.5.x. - qemu/libvirt versions differ between the test and production areas and must be standardized.
- The upgrade involves both
h84randky10sp3repositories.
Diagnostic Procedure
- Complete readiness checks and inspect
check.logbefore the upgrade. - Reconnect one non-critical host first after the platform upgrade for grayscale acceptance.
- Check qemu/libvirt/glib2 versions and the actual VM QEMU version after component upgrades.
Cause
In addition to upgrading the control plane, this procedure aligns qemu/libvirt versions for feature support and version convergence. Dual management and dual repositories require grayscale platform upgrade and host-reconnection acceptance before the component upgrade.
Resolution
- Preparation
- Risk level: high.
- Run the readiness-check script and check
zsha2 status. - Disable global high availability.
- Reserve one non-critical host for reconnection acceptance.
- Stop all backup tasks.
- Environment preparation
- Run the readiness check:
tar zxvf zstack-upgrade-check-master.tar.gz
cd zstack-upgrade-check-master
bash exec_tool.sh -p [MN_admin_password]
cat ./log/check.log
- Expected result: the upgrade environment has no blocking item.
- Adjust database timeouts and restart
mariadb:
wait_timeout=28800
interactive_timeout=28800
Then run:
systemctl restart mariadb.service
- Expected result: database timeout risk is reduced during the upgrade.
- Update global configuration:
UpdateGlobalConfig category=storageDevice name=enable.multipath value=ignore
UpdateGlobalConfig category=applianceVm name=connect.timeout value=1200
UpdateGlobalConfig name=update.os.parallelismDegree category=cluster value=5 or 10
UpdateGlobalConfig name=update.os.parallelismDegree category=host value=10
- Expected result: upgrade and host-reconnection parameters are prepared.
- Back up both management-node databases:
zstack-ctl dump_mysql --file-name 4.x-mn1
zstack-ctl dump_mysql --file-name 4.x-mn2
- Expected result: a platform rollback basis is available.
- Grayscale-upgrade the platform to 5.5.x
- Update both repositories on the dual management nodes:
bash zstack-upgrade -r ZStack-x86_64-DVD-5.5.1-260112-h84r-Enterprise.iso
bash zstack-upgrade -r ZStack-x86_64-DVD-5.5.1-260112-ky10sp3-Enterprise.iso
- Expected result: management nodes have the target-version repositories.
- Identify the VIP node:
zsha2 status
- Expected result: the HA-upgrade execution node is identified.
- Extract and authorize the HA package:
tar zxvf ZStack-Multinode-HA-Suite.tar.gz
chmod +x zsha2 zstack-hamon
- Expected result: HA upgrade tools are ready.
- Stop MN services and upgrade the HA suite:
zsha2 stop-node
./zsha2 upgrade-ha -gencfg=true
- Expected result: the dual-management HA suite is upgraded.
- Perform the platform grayscale upgrade:
zsha2 upgrade-mn -grayscale -yes -db-root-pw $mysql_root_password -peerpass $peer_mysql_root_password $zstack_bin
- Expected result: the platform is upgraded to
5.5.x.
- Check after the upgrade:
zstack-ctl status
zsha2 status
- Expected result: management nodes and HA are normal.
- Grayscale acceptance
- Log in to the UI and check hosts, primary storage, image servers, and other resources.
- Expected result: all resources are connected.
- Manually reconnect one non-critical host first.
- Expected result: the host upgrade status becomes
Upgraded.
- Check:
zstack-cli QueryAgentVersion
- Expected result: the Agent version is recorded correctly.
- Check by storage type:
- SharedBlock:
vgs,lsblk,multipath -ll, and I/O error logs - Ceph:
ceph -s - Management-node logs:
management-server.log - VMs: console
pingconnectivity - Expected result: hosts, storage, and workloads are normal.
- Reconnect other hosts in sequence if no issue is found.
- Disable the grayscale variable and enable global high availability:
QueryGlobalConfig category=upgradeControl name=grayscaleUpgrade
UpdateGlobalConfig name=grayscaleUpgrade category=upgradeControl value=false
- Expected result: the platform-upgrade process is complete.
- Upgrade qemu / libvirt / glib2
- Keep using both
5.5.xrepositories on the dual management nodes. - Upgrade one host first:
qemu-storage-daemonqemu-kvmlibvirtglib2- Expected result: validation completes on one host first.
- After one-host validation, perform the same upgrade for the cluster.
- Use:
QueryLongJob uuid=xxx
Track progress.
- Use batch SSH with
rpm -q qemu-kvm libvirt glib2to verify version consistency.
- Expected result: both test and production areas are aligned to the target versions.
- After the
qemuupgrade, migrate or restart VMs and run:
virsh qemu-monitor-command $VMuuid --hmp info version
Check the actual QEMU version.
- Expected result: VMs run with the new QEMU version.
Verification
- Verify that the platform version is
5.5.x. - Verify that the grayscale host and subsequently reconnected hosts are normal.
- Verify that
QueryAgentVersionis correct. - Verify that qemu/libvirt/glib2 match target versions.
- Verify that the VM QEMU version is updated.
Risks and Rollback
- Risk: management nodes are unavailable during the upgrade and cannot provision VMs or volumes.
- Risk: qemu/libvirt upgrades affect virtualization compatibility and require adequate validation.
- Risk: a qemu upgrade requires migration or restart before VMs use the new version.
- Risk level: high.
- Rollback: return dual management to single management, then restore the previous repository, installer, and database.