Scenario
- Product:
ZCF - Component:
ZStack Cloud - ZStack Cloud version:
5.4.x - Operating system:
H84r - Storage involved:
ZCE-X - Deployment: Dual management nodes
- Trigger: The dual-management platform must be upgraded through grayscale deployment to a newer LTS patch release.
Symptoms
- The current platform version is
5.4.x. - The target version is
5.4.x. - This change upgrades only ZStack Cloud, not
qemu/libvirt/kernel. - One host must be reconnected first to validate the agent and workload state.
Assessment
- Run the precheck and inspect
check.logbefore upgrade. - Reconnect one non-critical host for grayscale validation after upgrade.
- Reconnect remaining hosts only after the first validation passes.
Cause
Although this change does not modify core virtualization-component versions, it is still a dual-management grayscale upgrade. The key risks are agent upgrade, management-node switching, database timeouts, and environmental compatibility. Complete precheck, preparation, and grayscale validation are required.
Resolution
- Preparation
- Risk level: High.
- Applicable only to
x86 + H84renvironments. - Disable global high availability.
- Select one non-critical host for grayscale reconnection validation.
- Stop all backup jobs.
- Precheck and environment preparation
- Run the precheck package:
tar zxvf zstack-upgrade-check-master.tar.gz
cd zstack-upgrade-check-master && bash exec_tool.sh -p [MN_admin_password]
cat ./log/check.log
- Expected result: Compatibility and blocking conditions are checked.
- Upload the ISO, upgrade script, HA package, and bin file, and verify
md5/commit.
- Expected result: Upgrade materials are correct.
- Set database timeouts, then restart MariaDB:
wait_timeout=28800
interactive_timeout=28800
systemctl restart mariadb.service
- Expected result: Database timeouts are avoided during upgrade.
- Adjust global configuration for the environment:
UpdateGlobalConfig category=storageDevice name=enable.multipath value=ignore
UpdateGlobalConfig category=applianceVm name=connect.timeout value=1200
UpdateGlobalConfig name=update.os.parallelismDegree category=cluster value=5 or 10
UpdateGlobalConfig name=update.os.parallelismDegree category=host value=10
- Expected result: Parameters are prepared for grayscale upgrade and host reconnection.
- Back up the databases on both management nodes.
- Expected result: A platform rollback baseline is available.
- Perform grayscale upgrade
- Update the repository on both management nodes:
bash zstack-upgrade -r ZStack_Alibaba_Cloud-x86_64-DVD-5.4.6-h84r.iso
- Expected result: The upgrade repository is switched.
- Locate the VIP node:
zsha2 status
- Expected result: The node for
upgrade-hais identified.
- Extract the HA package and grant execute permission:
tar zxvf ZStack-Multinode-HA-Suite.tar.gz
chmod +x zsha2 zstack-hamon
- Expected result: HA upgrade tools are executable.
- Stop management-node services:
zsha2 stop-node
- Expected result: Management nodes are ready for upgrade.
- Upgrade the HA suite on the VIP node:
./zsha2 upgrade-ha -gencfg=true
- Expected result: The HA suite is upgraded.
- Perform grayscale upgrade:
zsha2 upgrade-mn -grayscale -yes -db-root-pw $mysql_root_password -peerpass $peer_mysql_root_password $zstack_bin
In a single-management environment, bash zstack-installer.bin -u --grayscale true is for reference.
- Expected result: ZStack Cloud is upgraded to
5.4.xin grayscale mode.
- Grayscale validation after upgrade
- Check status:
zstack-ctl status
zsha2 status
- Expected result: Management-node and HA status are normal.
- In the UI, verify that hosts, primary storage, image servers, and other resources are connected.
- Expected result: Platform resources are connected.
- Reconnect one non-critical host manually.
- Expected result: Its agent is upgraded without affecting workloads.
- Check the agent-version record:
zstack-cli QueryAgentVersion
- Expected result: The version record is correct.
- Check the relevant storage type:
- SharedBlock:
vgs, multipath, SAN links, and/var/log/messages. - Ceph:
ceph -s. - Local storage:
xfs, device names, and mount-path logs. - Expected result: Host storage and workloads are normal.
- Reconnect remaining hosts after grayscale validation passes.
- Disable grayscale mode:
QueryGlobalConfig category=upgradeControl name=grayscaleUpgrade
UpdateGlobalConfig name=grayscaleUpgrade category=upgradeControl value=false
- Expected result: Grayscale mode is closed.
- Enable global high availability.
- Expected result: The upgrade is complete.
Verification
- Verify normal
zstack-ctl statusandzsha2 status. - Verify normal workloads on the first reconnected host.
- Verify the
QueryAgentVersionrecord. - Verify that all platform resources are connected.
Risks and rollback
- Risk: Management nodes, APIs, and new resource provisioning are unavailable during upgrade.
- Risk: Inadequate prechecks can cause host or primary-storage connection failures during grayscale deployment.
- Risk: Browser cache can prevent the upgraded UI from loading until the cache is cleared.
- Risk level: High.
- Rollback includes decoupling dual management to single management, stopping
zsha2/keepalived/zstack-ha, runningstop slave/reset slave all, rewritingDB.url, removing/usr/local/zstack, and restoring the previous repository, installer, and database withrestore_mysql.